The Development Programme Management Process A Establishing a review board for developments B Establishing review criteria and m

admin2016-06-30  38

问题                 The Development Programme Management Process
A Establishing a review board for developments
B Establishing review criteria and mechanisms
C Continuously re-prioritising a potential list of projects
D Establishing reviewers for individual projects and stages
E Establishing team working environment
F Strengthening technical and commercial input
G Promoting the refinement of resource / budget
H Hand-holding the programme in its early life
Paul Smith was in need of suggestions on how to well-organise his seven projects under way.

选项

答案D

解析 题干意为:Paul Smith需要关于如何合理安排他的7个正在进行中的项目的建议。根据题干中数字“7”可知项目为多个,因而很可能各自处于发展的不同阶段,因此Paul Smith需要的是关于如何处理处于不同阶段的多个项目的意见。结合原文信息点可判断出“为各项目和阶段设立审查员”是一条很好的建议,故答案为D。
转载请注明原文地址:https://kaotiyun.com/show/CBIO777K
0

随机试题
最新回复(0)