The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, es

admin2010-01-28  48

问题 The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

选项 A、defining
B、estimating
C、planning
D、sequencing

答案B