The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estima

admin2009-09-20  39

问题 The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.

选项 A、estimating
B、defining
C、planning
D、sequencing

答案A

解析 估算活动历时的过程会用到活动工作范围、所需资源类型、估计的资源数量以及建立在资源可用性上的资源日历等信息。
转载请注明原文地址:https://kaotiyun.com/show/XLGZ777K
0

最新回复(0)