Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities

admin2010-01-17  36

问题 Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

选项 A、milestone
B、baseline
C、quality
D、work

答案D

解析 估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。
转载请注明原文地址:https://kaotiyun.com/show/aHGZ777K
0

相关试题推荐
随机试题
最新回复(0)