(72) is the process of obtaining the stakeholdrs’formal acceptance of the completed project scope. Verifying the scope includes

admin2010-01-28  39

问题 (72) is the process of obtaining the stakeholdrs’formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

选项 A、WBS Creation
B、Scope definition
C、Project acceptance
D、Scope verification

答案D

解析