(1)is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to repres

admin2009-05-15  37

问题 (1)is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.This method includes following types of dependcies orprecedence relationships: (2)the initiation of the successor activity, depends upon the completion of the predecessor activity. (3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.

选项 A、F-S
B、F-F
C、S-F
D、S-S

答案D

解析 PDM是以一种方块或矩形(或称为节点)来表示活动,并将它们用表示依存关系的箭线连接起来,以构建项目进度网络图的方法。这种方法包括了下列依存或前导关系:完成-开始(F-S),后续活动的开始依赖于前置活动的完成。开始-开始(S-S),后续活动的开始依赖于前置活动的启动。
转载请注明原文地址:https://kaotiyun.com/show/t1GZ777K
0

相关试题推荐
最新回复(0)