(73) was developed to make clear the interdependence between project tasks before those tasks are scheduled.

admin2010-01-28  28

问题 (73) was developed to make clear the interdependence between project tasks before those tasks are scheduled.

选项 A、Network Diagram
B、CPM
C、Gantt chart
D、PERT

答案D

解析