The (73) provides the project manager with the authority to apply organizational resources to project activities.

admin2010-01-28  42

问题 The (73) provides the project manager with the authority to apply organizational resources to project activities.

选项 A、project management plan
B、project charter
C、project human resource plan
D、project stakeholders

答案B

解析
转载请注明原文地址:https://kaotiyun.com/show/5SHZ777K
0

相关试题推荐
最新回复(0)