In the process of communication requirement analysis,the project manager should consider the number of potential communication c

admin2018-10-14  43

问题 In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication.According to Metcalfe’s Law,a project with 10 stakeholders has(    ) potential communication channels.

选项 A、10
B、45
C、50
D、100

答案B

解析 在沟通需求分析过程中,项目经理应将潜在的沟通渠道数目作为项目沟通复杂性的指示器。根据梅特卡夫定律,10个干系人的项目有45条潜在的沟通渠道。
沟通渠道数量=N(N一1)/2=10×9/2=45条。