To: Robert Williams, School of Architecture From: James. Johnson Subject: Air-conditioning Installation Costs for East Hall Date

admin2009-06-28  63

问题 To: Robert Williams, School of Architecture
From: James. Johnson
Subject: Air-conditioning Installation Costs for East Hall
Date: June 4, 2006
   I am writing to inform you of the costs of installing air-conditioning for the seven offices and two studio classrooms in East Hall.
Office and Classroom Installation
   Estimates were obtained from three contractors on the costs of covering the offices and classrooms.  All these three were in the $20,000 to $25,000 range. The work would take about three weeks.
   Because the central unit would be installed on the roof, some noise problems might occur during a four-or five-day period. And this work could be started from this weekend, and the  overtime labor costs of about $1,500 have been included in the estimates.
Additional Installation
   Because a larger installation, including a more powerful central unit, would he necessary to handle the halls and stairways, an additional $6,000 would be required for the equipment. If this additional work were delayed until a later time, a new central unit would be required along with changes in the pipe way.
Subject:  (46)   Costs for East Hall
Office and Classroom Installation
   1. Covering area: seven offices and two  (47)  
   2: Possible problem: some  (48)   might occur during a four- or five-day period
Additional Installation:
   1. Budget: $6,000
   2. A more powerful  (49)  is needed to handle the halls and stairways
   3. Additional installation postponement will result in changes in  (50)  


选项

答案noise problems

解析
转载请注明原文地址:https://kaotiyun.com/show/7mqK777K
0

最新回复(0)