A critical path for a project is the series of activities that determine_______by which the project can be completed.

admin2017-11-27  53

问题 A critical path for a project is the series of activities that determine_______by which the project can be completed.

选项 A、the earliest time
B、the latest time
C、the total time
D、the free time

答案A

解析 题目是问项目关键路径是项目一系列活动中的哪一步,事实上,确定项目关键路径应在项目最早期开始,故选A。
转载请注明原文地址:https://kaotiyun.com/show/AhHZ777K
0

相关试题推荐
随机试题
最新回复(0)