Read the article below about project management. Choose the best sentence from the opposite page to fill each of the gaps.
Read the article below about project management. Choose the best sentence from the opposite page to fill each of the gaps.
admin
2016-11-29
19
问题
Read the article below about project management.
Choose the best sentence from the opposite page to fill each of the gaps.
For each gap(8-12), mark one letter(A-G)on your Answer Sheet.
Do not use any letter more than once.
There is an example at the beginning(0).
Can Your Marketing Be Effective Without Project Management?
Are your projects flowing smoothly? Are you assigning responsibilities, deadlines and tasks, but it is just a headache to keep up? A likely problem is that tasks are not getting handed off well or at the right time to others.(0)G A project management system is not a cure-all, but it certainly is a start.
In marketing, I’m always amazed at the lack of formalised project management systems. 【P1】______They assume that the purpose of a detailed plan is the same as it would be for other repetitive activities like manufacturing. The purpose of a project plan in marketing is to coordinate many of the uncertain activities that happen. And possibly more importantly, a good project plan will coordinate the activities of your resource requirements. Not everything will be predictable, but if we can make even some of the unpredictable predictable, we will increase the likelihood of success.
Within a project plan, we can establish overall and individual process metrics. 【P2】______The value of these types of metrics is that they will allow you to take action during a project where and when you can still influence its success. Measur-ability is perhaps the most important feature of the project plan.
Project management covers all aspects of planning: coordinating activities and resources and forming a baseline from which to manage the project. 【P3】______Once a schedule is completed, it should be posted or made available to all stakeholders of the project. Constant updating should appear and be visible to all parties. A project plan is an active document, and should be used to manage the process. A schedule is the translation of the project plan into individual tasks, identifying durations, responsibilities, start and finish dates, resources, flow and milestones.
Everyone knows we cannot do enough planning, but it’s the time factor that prevents us, right? How much time does it really take to plan? From my experience you should use a baseline of around 5% of your project’s time in planning. Now, what happens if planning takes longer? You need to treat your planning process like any other process. Using a standard methodology, such as Lean Six Sigma and the toolset that it employs, will allow you the opportunity to get the most out of your planning cycle. 【P4】______I have found most companies actually enjoy planning, the collaboration and decision-making that take place during it. What everyone doesn’t like is the waste in planning, so get rid of it!
The first thing you can do is plan the planning process. Take 5% of your planning time to improve your planning. Set objectives, milestones, create key performance indicators and, most of all, create a standard work plan. 【P5】______Consider that if you significantly improve your planning process, you will stop fighting such an uphill battle and create considerable down-flow opportunities of greater savings. Try it!
Example:
A This gives everyone involved the same reference point.
B We will need metrics to produce information quickly.
C It will improve your planning process, removing the waste that you have accumulated in it.
D After doing this a few times, planning will become very easy, intuitive and more productive.
E There is more to project planning than this.
F Most marketers resist the idea, misunderstanding the role of detailed planning for marketing projects.
G Another problem may be that everyone’s priorities seem all mixed up, and one or two people or departments seem to be an enormous bottleneck.
【P3】
选项
答案
A
解析
所缺句子应说明“基线”的作用,与选项A提到的“这给了每个参与人相同的参照点。”相呼应,而且选项A中的everyone involved与后一句中的all stakeholders相呼应。
转载请注明原文地址:https://kaotiyun.com/show/AioO777K
本试题收录于:
BEC中级阅读题库BEC商务英语分类
0
BEC中级阅读
BEC商务英语
相关试题推荐
•Inthispartyoulistentwicetoalongconversation,interviewormonologue,andanswereightquestions.•Beforeyoulisten,
RichardWoodstartedtheinternetcompany,Bookstore,becausehefeltWhyisBookstore’scustomerservicesosuccessful?
•YouwillhearareportpresentedbyajournalistfromTokyo.•Foreachquestion23--30,markoneletter(A,BorC)forthecor
WhatuniquesituationdoesTelekomhavetoinstall?WhathashappenedtosomeofTelekom’sprojects?
HowtoapproachListeningTestPartTwo•Thispartisintwosections,Ineachsectionyoulistentofiveshortmonologues,spo
WhatdoesDansayabouthisappraisalinterview?AccordingtoDan,adisadvantageofworkingwithcustomersishavingto
•Lookatthenotesbelow.•Youwillhearananswerphonemessageaboutarrangementsforabusinesstrip.ConversationOne•Loo
•Lookatthenotesbelow.•YouwillhearajournalistphoningtheManagingDirectorofShipton’sFoodsabouthisfirm’swebsit
•Youwillheararadioreportaboutfamilybusinesses.•Foreachquestion23-30,markoneletter(A,BorC)forthecorrectans
YouwillhearapartofaspeechabouttheAsiancrisis.Choosethebestanswerforeachofthequestions(23—30).Markonele
随机试题
在我国生产同类商品的甲、乙企业均使用A商标,甲企业使用在先。乙企业注册在先,在乙企业注册商标核准以后,甲企业()
颌骨骨折最常见的临床体征是
根据《合同法》规定,债权人应自知道或者应当知道撤销事由之日起()年内行使撤销权。
孟波所在的上市公司2012年实行雇员股票期权计划。2012年3月25日,该公司授予孟波股票期权90000股,施权价3元/股,约定2013年11月25日起可以行权,行权前不得转让。2013年11月25日孟波以施权价购买股票90000股,当日该股票的公开市场价
生产型企业在进行生产能力核算时,应首先计算()的生产能力。
根据行政复议法律制度的规定,下列关于行政复议决定的表述中,不正确的是()。
对于经常项目与资本项目外汇管理分别有不同的规定,下列选项中不属于资本项目的是()。
()是remwever的模板文件的扩展名。
突破行政手段纵向联系的运用方式,向横向联系方向发展的行政方法是()
在现代企业制度下,企业作为独立的法人对注入企业的资本金具有
最新回复
(
0
)