( )is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time perio

admin2018-10-14  30

问题 (    )is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

选项 A、Planned value
B、Earned value
C、Actual cost
D、Cost variance

答案B

解析 挣值(Earned value)是在给定时期内实际完成工作的预算值。
转载请注明原文地址:https://kaotiyun.com/show/BSFZ777K
0

相关试题推荐
最新回复(0)