首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
31
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
Which of the following sentences can be inferred from the report?
选项
A、The reporter will dismiss the subcontractor sooner or later.
B、It will probably need more crew when dealing with the work indoors.
C、The work will fall farther behind if there is no extra electricians being added.
D、The framing, roofing, and siding is likely to have been finished by the middle of October if weather permitted.
答案
C
解析
转载请注明原文地址:https://kaotiyun.com/show/DKid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
Whowillmakeatelephonecall?
MarawasgoingtostaywithherfriendFannyforthreedays.Aweekbeforehertrip,shecalledFannytotellherwhenthetrain
Ifyou’reinvitedtoafriend’shomefordinner,keepinmindtheserulestobepolite.Firstofall,arriveontime(butnotea
In1826,aFrenchmannamedNiepceneededpicturesforhisbusiness.Buthewasnotagoodartist.Soheinventedaverysimplec
December25thisChristmasDay.ManyAmericansarebusywithChristmasandthewinterholidayseason.BuyingaChristmastreeis
Itisveryimportantforacompany______agoodofficesecretary.
Writealetteraccordingtothefollowingrequest,writeyouranswerontheANSWERSHEET.代理关系感谢贵行×年×月×日来
Required,honour,dispatched,resulted,received,irrevocable,release,declared,prepared,handedGoodsshouldnotbe【21】di
______marrythatman,shewouldearnherlivingasawaitress.
To:ALLSTAFFSubject:RecyclingCampaignDate:July1,2007Inanon-going,earth-friendlyefforttorecyclemorewasteforabe
随机试题
已知隐函数z=f(χ,y)由方程e-χy=yz+χ2y=1所确定,求。
A.肝B.肾C.脾D.肺与汗液的排泄关系最密切的是
关于吸气性呼吸困难的临床表现,错误的是()
患儿,3岁,以突然高热、进行性呼吸困难入院,怀疑为中毒型痢疾。为早日检出痢疾杆菌,护士留取大便正确的做法是
背景材料:某公路路面工程,里程桩号为K5+000~K29+000,总长度为24km。路面结构层分为级配砾石底基层、水泥稳定碎石基层、沥青面层(单层)。建设单位(业主)希望施工单位尽可能用最短时间完成该路面工程施工。施工单位根据自己的能力准备组织2个路面施
近年来,各种搞笑、轻浮的网络语言大规模地侵入了传统汉语的领地,影响大有不断壮大之势。对待网络语言,虽然学界和社会上还有很多不同的声音,但可以肯定的是,如果缺乏及时合理的鉴别和引导,任其自流,无疑将会消解传统汉语的诗意和韵味,割裂汉语的文化传承脉络,同时也将
小李考上了清华,或者小孙没考上北大。增加以下哪项条件,能推出小李考上了清华?
A、Peoplehavedifferenttastes.B、Eachofthemownsarestaurant.C、Thewomanshouldtellhimwhatshethinks.D、Manycustomers
TheVictorianAgewaslargelyanageof
Barbecuinghasbecomean【C1】______partofAmericanlife,asbarbecuegrillsarefoundinthemajorityofAmericanhomes.P
最新回复
(
0
)