Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco

admin2011-06-01  23

问题                             Wolfe Constructions
                    121 Fifteenth Street Melbourne 200430
                    88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
Which of the following sentences can be inferred from the report?

选项 A、The reporter will dismiss the subcontractor sooner or later.
B、It will probably need more crew when dealing with the work indoors.
C、The work will fall farther behind if there is no extra electricians being added.
D、The framing, roofing, and siding is likely to have been finished by the middle of October if weather permitted.

答案C

解析
转载请注明原文地址:https://kaotiyun.com/show/DKid777K
0

最新回复(0)