Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74)

admin2010-05-08  42

问题 Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.

选项 A、scope statement
B、activity list
C、project charter
D、project schedule

答案D

解析
转载请注明原文地址:https://kaotiyun.com/show/F4HZ777K
0

相关试题推荐
随机试题
最新回复(0)