问题 Theearnedvaluetechniqueisacommonlyusedmethodofperformancemeasurement.Itintegratesprojectscope,cost,andschedulemeasurestohelptheprojectmanagementteamassessprojectperformance.Ifaproject’sSchedulePerformanceIndex(SPI=EV/PV)valuelessthan1.0,itmeansthat______.

选项 A、theprojectisaheadofitsplannedschedule
B、lessworkwascompletedthanwasplanned
C、thecostoverrunforworkcompleted
D、thecostunder-runofperformancetodate

答案B

解析 根据《系统集成项目管理工程师教程》(全国计算机专业技术资格考试办公室组编)第9.5.3小节的内容可知,SPI值小于1表示实际进度落后于计划进度。因此,正确答案应选B。