Tne ( ) technique involves using project characteristics in a mathematical model to predict activity parameters,such as cost,

admin2018-10-14  34

问题 Tne (    ) technique involves using project characteristics in a mathematical model to predict activity parameters,such as cost,budget,and duration.Models can be simple or complex.

选项 A、cost aggregation
B、reserve analysis
C、parametric estimating
D、funding limit reconciliation

答案C

解析 (参数估算)技术将项目特性放入数学模型中来预测项目活动的各种参数,诸如成本、预算和持续时间等。模型可以是简单的也可以是复杂的。
A为成本汇总,B为储备分析,C为参数估算,D为资金限制平衡。