(74)is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

admin2008-04-01  26

问题 (74)is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

选项 A、Planned value
B、Earned value
C、Actual cost
D、Cost variance

答案B

解析 挣值是在给定时期内按进度活动或WBS部件所完成工作的预算值。
转载请注明原文地址:https://kaotiyun.com/show/WBGZ777K
0

随机试题
最新回复(0)