Configuration management is focus on the specification of both the deliverables and the processes;While( )is focused on ident

admin2019-09-25  28

问题 Configuration management is focus on the specification of both the deliverables and the processes;While(    )is focused on identifying,documenting,and approving or rejecting changes to the project documents,deliverables,or baselines.

选项 A、cost management
B、change management
C、configuration management
D、capacity management

答案B

解析 配置管理关注可交付成果和过程的规范;而变更管理关注于识别、记录和批准或拒绝对项目文档、可交付成果或基线的更改。