Project Time Management includes the processes required to manage timely completion of the project, these processes interact wit

admin2011-01-29  40

问题 Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

选项 A、Develop Schedule
B、Estimate Activity Resources
C、Define Activities
D、Sequence Activities

答案A

解析 项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。