首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Central Engineering Company Board of Directors Meeting Wednesday, November 15, 20 8:30 A.M.-11:30 A.M. Place: Suite
Central Engineering Company Board of Directors Meeting Wednesday, November 15, 20 8:30 A.M.-11:30 A.M. Place: Suite
admin
2011-01-13
104
问题
Central Engineering Company
Board of Directors Meeting
Wednesday, November 15, 20 8:30 A.M.-11:30 A.M.
Place: Suite 10
AGENDA
1. Hiring challenges Jorgen Spelman
2. Management changes Narelle Dundee
3. Financial report Madeira Jones
4. Technology upgrades Jerry Carver
FAX COVER SHEET
CENTRAL ENGINEERING COMPANY
294 Green Street
Brasilia
Brazil
Tel: (55) 61 3420 4015
Fax: (55) 61 3420 4017
To: Ruben Baker
From: Narelle Dundee
Date: November 15, 20
Pages: 1
Ref: Results of the board meeting
Message:
I hope your business trip is going well. Today’s meeting went well for the most part, even though it began 30 minutes late. Jorgen wasn’t there at the beginning, so I used his time slot to give my report. Jorgen finally arrived at 9:30 and gave his report. The board members were surprised to hear that job applicants complain about our salary offers. Jerry’s report really shocked and upset the board. Fortunately, Madeira’s report had the opposite effect. Everyone was happy to hear about our great profits.
The technology upgrades report didn’t go so well. Jerry had to leave the meeting before his report because there was an Internet problem in the Electrical Engineering department. Because of this, the presenter for our third agenda item read Jerry’s report, and it was a bit confusing. She didn’t really know what she was talking about and couldn’t answer questions satisfactorily. We decided to ask Jerry to provide written answers to questions raised by board members during the meeting.
Because we started late, we finished a half hour late, but we still had to hurry to finish within the allotted time. We decided to make the next board meeting a half-hour longer to give more time for discussion and questions.
How long did the meeting last?
选项
A、
B、
C、
D、
答案
C
解析
The meeting started late and ended late but still lasted the three hours that it was scheduled to last. Choice (A) is the amount of time they plan to add to the next meeting. Choice (B) is half an hour less than the scheduled time. Choice (D) will be the length of the next meeting.
转载请注明原文地址:https://kaotiyun.com/show/lRid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
InAmsterdam(阿姆斯特丹),thereisanunusualChildrenRestaurant.Itisrun(经营)bychildren.Fromthemanagertothecooks,waiter
It’sapitythatshedidn’tattendthatimportantmeeting.It’sapitythatshe______thatimportantmeeting.
Whenisthemeetinghold?
Ellenlefthomeearlyyesterdaybecauseatnineo’clockshewasgoingtostartworkatacompanyinthecity.Shewasonlyeigh
Ellenlefthomeearlyyesterdaybecauseatnineo’clockshewasgoingtostartworkatacompanyinthecity.Shewasonlyeigh
InAmsterdam(阿姆斯特丹),thereisanunusualChildrenRestaurant.Itisrun(经营)bychildren.Fromthemanagertothecooks,waite
Listany5illegalcontractsstrictlysocalled.
Fromatechnicalpointofview,internationaleconomicintegrationcanbealimitedprocess,i.e.theeliminationoftariffsan
GreenConstructionCo.429MillsRoadMinneapolis,MN55440-0710Tel:(763)555-2100Fax:(763)555-2252
随机试题
乳酸脱氢酶由几种亚单位组成
A.双螺旋模型B.核小串珠结构C.Z-DNA结构D.茎环结构E.帽子结构DNA超螺旋结构
患者,男,56岁,有高血压病史4年。体检:血压156/96mmHg,无主动脉狭窄。医师处方依那普利片控制血压。该患者用药过程中可能发生的典型不良反应是()。
某建设项目静态投资为10000万元,项目建设前期年限为1年,建设期为2年,第一年完成投资40%,第二年完成投资60%。在年平均价格上涨率为6%的情况下,该项目价差预备费应为()万元。【2016年真题】
土中水有固、液、气三种形态,其中液态水有( )。
下图为一齿轮传动,图中数字为齿轮数,如果缸Ⅰ的转速n1=730r/min,问:轴Ⅵ的转速应是多少?其转向与轴I相同吗?
出现下列情况中的()时,税务机关可以要求纳税人提供纳税担保。
某房地产公司为增值税一般纳税人,从事多业经营,2018年2月发生如下业务:(1)将某地块开发建造商品房,当月全部售出,本月收到售房款3600万元,另外代收房屋专项维修基金240万元。2015年购置该地块时支付地价款1800万元。(2)经营酒店取得餐饮收
寺院里丢失了一袋香火钱,方丈找到甲、乙、丙三个小和尚来询问,三个人逐一陈述,甲说:“我没偷。”乙说:“甲偷了。”丙说:“我没偷。”在一旁的丁了解真相,并发表意见说:“你们三个人中只有一个人偷了,且只有一个人说对了。”因此,他们三人中偷了香火钱的是(
下列关于Winmail邮件服务器描述中,错误的是()。
最新回复
(
0
)