(2010年上半年)(74)is primarily concerned with defining and controlling what is and is notincluded in the project.

admin2015-05-26  4

问题 (2010年上半年)(74)is primarily concerned with defining and controlling what is and is notincluded in the project.

选项 A、ProjectTimeManagement
B、ProjectCostManagement
C、ProjectScopemangent
D、ProjectCommunicationsManagement

答案C

解析 项目范围管理主要关注定义和控制“什么在项目中,什么不在项目中”。