问题 (2009年下半年)(73)is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them.

选项 A、PERT
B、AOA
C、WBS
D、PDM

答案D

解析 (73)是一种在关键路径法中用来编制项目进度网络图的方法,它用盒子或矩形(称为节点)来代表活动,并将节点用箭头连接起来,以表达节点之间的逻辑关系。