Estimating activity durations uses information on activity scope of(39),required resource types,estimated resource quantities,an

admin2019-06-06  37

问题  Estimating activity durations uses information on activity scope of(39),required resource types,estimated resource quantities,and resource calendars.

选项 A、milestone
B、baseline
C、quality
D、work

答案D

解析
转载请注明原文地址:https://kaotiyun.com/show/pOFZ777K
0

相关试题推荐
最新回复(0)