Before a project schedule can be created,the schedule maker should have a(73),aneffort estimate for each task, and a resource li

admin2016-09-08  48

问题 Before a project schedule can be created,the schedule maker should have a(73),aneffort estimate for each task, and a resource list with availability for each resource.

选项 A、work breakdown structure
B、baseline
C、software requirements specification
D、plan

答案A

解析 本题目翻译:制定项目进度计划之前,制定计划者需要任务分解结构(WBS)、各任务的工作量估计以及可能得到的资源列表。根据项目管理计划制定原则,得到答案A。
转载请注明原文地址:https://kaotiyun.com/show/s4GZ777K
0

相关试题推荐
最新回复(0)