In project management,a(75)is a list of a project’s。milestones,activities,and deliverables, usually with intended start and fini

admin2014-05-07  3

问题 In project management,a(75)is a list of a project’s。milestones,activities,and deliverables, usually with intended start and finish dates.Those items are often estimated in terms ofresourceallocation,budget and duration,linked by dependencies and scheduled events.

选项 A、schedule
B、WBS
C、SOW
D、charter

答案A

解析 在项目管理中,(75)是一个项目的里程碑、活动和交付物的列表,通常还包括预期的开始日期和完成日期。这些项目往往是估计在资源配置方面,预算和时间依赖关系,联系和安排的活动。
A.进度表
B.WBS
C.SOW
D.项目章程
转载请注明原文地址:https://kaotiyun.com/show/tdHZ777K