( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing

admin2019-09-25  18

问题 (    )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for tlle remaining work.

选项 A、Schedule forecasts
B、Schedule compression
C、Change requests
D、Data analysis

答案B

解析 翻译:(    )技术用于通过快速跟踪或破坏剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。
A.进度预测  B.进度压缩  C.变更请求  D.数据分析
转载请注明原文地址:https://kaotiyun.com/show/uJHZ777K
0

相关试题推荐
最新回复(0)