Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
65
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
Which of the following project had NOT been finished according to the report?
选项
A、Framing on the 14# townhouse
B、The foundation for the whole complex
C、The electrical and plumbing work
D、Framing on the gym
答案
C
解析
转载请注明原文地址:https://kaotiyun.com/show/xKid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
Weight(体重)isoneofthetaboosubjects.InAmerica,itisOK,orevengood,tobethinbutitisanembarrassment(尴尬)tobeov
—Yourcitylooksbeautiful!—Yes.Lotsoftreesandgrass_________lastyear.
Mymotherarrived________Beijingtwodaysago.
Thoughthecityisnoisy,mostpeopleliketoliveinit.Therearereallymanythingstoseeandenjoyinacity.Thestreet
Thoughthecityisnoisy,mostpeopleliketoliveinit.Therearereallymanythingstoseeandenjoyinacity.Thestreet
A、July.B、August.C、September.D、October.C当男士问八月是否能出货时,女士给予了否定回答,她认为可能要到“MidSeptember”,所以选项C为正确项。
ExcelonTravelServices,Inc.711MarketStreetSanFrancisco,Cali
Effectiveplanninghelpsanorganization______tochangebyidentifyingopportunitiesandavoidingproblems.
Youcannot,asamanager,______entirelyonstatisticstogaugeemployeeperformance,becausestatisticscanoftenbemisleading.
随机试题
A.代谢性酸中毒B.代谢性碱中毒C.呼吸性酸中毒D.呼吸性碱中毒外科病人最常见的酸碱平衡失调是
A.芽胞B.鞭毛C.异染颗粒D.荚膜E.菌毛肺炎链球菌具有的结构
项目管理软件应用的步骤包括:①确定项目管理软件应用的范围;②确定项目管理软件应用的目标;③确定项目管理软件应用的需求;④项目管理软件的选择;⑤项目管理软件应用规划;⑥项目管理软件应用实施。这些步骤的正确顺序应为()。
陈甲继承了一套房屋后发现,被继承人陈某曾与天经公司签订地役权合同,为满足陈某观景的需要,陈某向天经公司支付100万元,天经公司在20年内不得在自己建造6米以上的建筑。现在尚在合同履行期限内,但天经公司已经在自己的厂区建造了一栋8米高的厂房。陈甲在办理产权
投保人申报的被保险人年龄不真实,并且其真实年龄不符合合同约定的年龄限制的,保险人可以()。
根据商业银行法律制度的规定,单位定期存款到期不取,逾期部分支取的计息规则是()。
儿童心理失调是由婴儿在分娩过程中受到的压力而导致的。这一点已经得到了证实——人们发现母亲分娩的时间和婴儿出生后第1个月中啼哭的时间有正比的关系。下面哪项如果正确,最不能质疑作者的观点?
通过探求立法者在制定民事法律规范的意图进行民法解释的方法是()
A、 B、 C、 D、 A
WhatisanElNinoAnElNinoisatemporarychangeintheclimateofthePacificOcean,intheregionaroundtheequator.Y
最新回复
(
0
)