With a clear sow a contractor completes work as specified,but the buyer is not pleasedwith the result.The contract is considered

admin2014-05-07  34

问题 With a clear sow a contractor completes work as specified,but the buyer is not pleasedwith the result.The contract is considered to be (75).

选项 A、incomplete because the buyer is not pleased
B、incomplete because the specs are incorrect
C、complete because the contractor meets the terms and conditions of the contract
D、complete because the contractor is s~isfied

答案D

解析 本题的含义是:
  根据明确的工作说明书,承包商按规定完成工作,但是买方对结果不满意。这个合同被认为是:   
A.未完成的,因为买方不满意
B.未完成的,因为规格不正确
C.完成的,因为承包商满意
D.完成的,因为承包商满足了合同的条款和条件
转载请注明原文地址:https://kaotiyun.com/show/y2HZ777K
0

最新回复(0)