Establishing a project management timetable involves listing milestones, activities, and(74)with intended start and finish dates

admin2016-09-08  44

问题 Establishing a project management timetable involves listing milestones, activities, and(74)with intended start and finish dates, of which the scheduling of employees may be anelement.

选项 A、relationships
B、resources
C、stakeholders
D、Deliverables

答案D

解析 本题目翻译:建立项目管理的时间表需要里程碑列表、各活动,以及含有估计开始和结束时间的可交付物,其中员工的调度被看作为元素。根据项目管理计划制定原则,得到答案D。