(20)involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to p

admin2009-05-15  35

问题 (20)involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

选项 A、Metrics
B、Measurement
C、Benchmarking
D、Baseline

答案C

解析 基准分析涉及到将实际或计划的项目实践与其他项目进行比较,以产生改进的思想并提供一个测量绩效的基准。所谓其他项目,既可以是执行组织内部的,也可以是外部的。既可以是同一个应用领域的,也可以是其他应用领域的。
转载请注明原文地址:https://kaotiyun.com/show/41GZ777K
0

相关试题推荐
最新回复(0)