Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more

admin2012-03-26  31

问题 Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?_____

选项 A、Scope Planning
B、Scope Verification
C、Scope ChangeControl
D、Scope Definition

答案D

解析 以下哪一个项目范围管理过程涉及的主要项目可交付物可细分为更小、更易于管理的组成部分?范围定义(ScopeDefinition)。