首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
专升本
The clever boy made a hole in the wall, ______he could see______was going on inside house.
The clever boy made a hole in the wall, ______he could see______was going on inside house.
admin
2019-01-15
65
问题
The clever boy made a hole in the wall, ______he could see______was going on inside house.
选项
A、which; what
B、through which; what
C、through that; what
D、what; that
答案
B
解析
through which引导定语从句,through which即through the hole,在定语从句中作状语。what引导的是see的宾语从句,并作从句的主语。
转载请注明原文地址:https://kaotiyun.com/show/8kaC777K
本试题收录于:
英语题库成考专升本分类
0
英语
成考专升本
相关试题推荐
Sometimeago,astoreadvertisedrebuiltvacuumcleanersofanationallyknownbrandattheabsurdly(荒谬地)lowpriceof$12.50
Iftheteacherasksaquestion,youareexpectedtogiveananswer.Ifyoudonotunderstandthequestion,youshouldraiseyour
Heshouldn’thavecomebackalive.CaptainJ.H.HedleywasBritishpilotinWorldWarI.Hefellvictimtoabitofmisfortune
A.MaybeIshouldcallataxiB.canyouhelpmeC.it’sthesecondleftD.notreallyE.atthetrafficlightsF.N
Youreallyhavetogetveryoldbeforeyourealizeyou’reold.I’minmymiddlefiftiesandIdon’tfeel【C1】______yet.However,
A.SeeyouthiseveningB.I’vegottarunC.SeeyouagainD.Iprobablywon’tbebackforsupperE.I’llgototheofficeF.Ta
A.SeeyouthiseveningB.I’vegottarunC.SeeyouagainD.Iprobablywon’tbebackforsupperE.I’llgototheofficeF.Ta
A.SeeyouthiseveningB.I’vegottarunC.SeeyouagainD.Iprobablywon’tbebackforsupperE.I’llgototheofficeF.Ta
Likefinefood,goodwritingissomethingweapproachwithpleasureandenjoyfromthefirsttastetothelast.Andgoodwriters
HeAwillnotBborrowyouthemoneyCevenifyouDask.
随机试题
冈崎片段是指
患儿,男,11个月。发热、咳嗽2天,以肺炎收入院。入院第2天,突然烦躁不安、呼吸急促,发绀。查体:体温38℃,呼吸70次/分,心率186次/分,心音低钝,两肺细湿哕音增多,肝肋下3.5cm。该患儿此时治疗措施最关键的是
变应性鼻炎鼻分泌物涂片检查可见
A.敏感化作用B.拮抗作用C.无关作用D.增加毒性E.增加疗效磷霉素使细菌细胞壁受损变薄利于阿莫西林进入菌体属于()。
患儿,女,8个月,因“发热1天"入院,入院查体:T39.8℃,心率146次/分,呼吸52次/分,神志清楚,精神倦怠,查体时突发抽搐1次,表现为意识丧失,双眼向上凝视,面色口唇发绀,四肢抽动,持续十余秒后自行缓解。遵医嘱应首选的抗惊厥药物是
如图所示的系统中,已知轮C质量为M,半径为R,物体A质量也为M,弹簧刚度为k。则系统的自振频率为()。
根据《固定资产投资项目节能评估和审查暂行办法》,下列关于项目节能评估的说法中,正确的有()。
某房屋建筑工程,建设单位与施工单位在工程质量保修书中对保修期限作如下规定,其中符合《建设工程质量管理条例》规定的有()。
【背景资料】某市政工程,合同总工期为10个月,施工单位根据施工方案绘制网络计划图如下图所示(单位为月)。【问题】指出关键线路及关键工作。
在双代号时标网络计划中,箭线中波形线的水平投影长度表示()。