首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
As the windiest country in Europe, the United Kingdom’s wind power potential is larger than the rest of Europe put together. Hal
As the windiest country in Europe, the United Kingdom’s wind power potential is larger than the rest of Europe put together. Hal
admin
2013-02-03
19
问题
As the windiest country in Europe, the United Kingdom’s wind power potential is larger than the rest of Europe put together. Half of this resource is in Scotland. The UK’s government has promised to generate 10% of their electricity using renewable resources. Wind power is seen to be the answer to doing this. The UK has issued wind farm licences to produce as much electricity as about six nuclear power stations. This policy has found favour with the public who support the search for cleaner energy sources.
Until 1989, Denmark was the only European state that had installed wind turbines for generating electricity. After 1989, other European countries followed suit developing support mechanisms for developing renewable energy and particularly wind power. Since 1994 the remaining European countries have also really started to support wind power station installation. Countries offer different levels of support. Some governments have paid companies premiums to maintain their competitive edge while others have given investment subsidies to foster the development of technology. Tax incentives have also been offered.
Nature provides us with indications for the best sites for wind turbine installation. Wind force and direction can be observed by leaning trees. This can most frequently be seen in open countryside and areas near coastlines and it is here, particularly in elevated spots clear of trees or buildings which obstruct the current of air, that wind farms have mostly been erected. Massive wind turbines, twice the size of conventional turbines, are also being developed for use offshore, as it is there that the strongest and most constant winds are found.
Believing that wind energy has no disadvantages is easy--it is clean, efficient and comparatively inexpensive and it creates no pollutants or emissions during operations. The electricity generated in the first 6 to 9 months of operation by a typical wind turbine will usually meet its manufacturing costs. However, wind farms are frequently regarded as a type of visual pollution because of their common locations on hilltops. It is inescapable that sites with the most wind are usually the most beautiful, and because they are built in wild, remote and untouched settings their impact is all the more noticeable. This is one of the most controversial questions when deciding on wind farm locations. Thus the setting of wind farms ought to be done with the greatest sensitivity. When turbines are due for decommission, the entire structure can be wholly recycled or removed and the cost of total site restoration can usually be completely met by the scrap value.
Wind turbines blades are made of glass fibre or wood epoxy and they can be of a diameter of 30 to 60 metres. The blades of the wind turbine generator are turned by the wind. The blades are joined to the hub that is in turn connected to the gear shaft. When the wind blows, the blades and hub turn the shaft that revolves within the generator; that then produces electricity. The power created is dependent on the blade size and the swept area. The speed of the wind and its availability are also key variables to be considered. The electricity is then moved to either the grid for regional use or to supply power to a stand-alone facility.
European operational capability was 2,500 megawatts in total by the end of 1995. By the end of 1996 it had increased to 3,400 MW and at the end of 1997 to 4,600 MW. There were steady increases in growth (40% per annum) over the following 6 years and the forecast is that this growth rate will persist. This is in contrast to practically zero growth in traditional fossil fuel energy production. Nonetheless, even at existing production levels, only 2% of potential energy is being exploited. In due course therefore wind farms may well satisfy 20% of total European power requirements. The European country with the most operational capacity is Germany. This is mostly down to the level of support given to wind power by Germany’s government. It has also been helped by recent innovation in the field of turbine development.
The UK’s government promised to generate ______ using renewable resources.
选项
答案
10% of their electricity
解析
(第一段第三句话明确提到The UK’s government has promised to generate 10% of their electricity using renewable resources.)
转载请注明原文地址:https://kaotiyun.com/show/JGyK777K
本试题收录于:
A类竞赛(研究生)题库大学生英语竞赛(NECCS)分类
0
A类竞赛(研究生)
大学生英语竞赛(NECCS)
相关试题推荐
Accordingtorecentsurveys,72%ofallAmericansbelievethattheUnitedStatesgovernmentis【C1】hi______informationaboutUFOs
EachoftheninesquaresinthegridmarkedAltoC3shouldincorporateallthelinesandsymbolswhichareshowninthesquares
WhilebaseballisoftendescribedasthenationalsportoftheUnitedStatesofAmerica,itprobablydevelopedfromaneighteent
WhilebaseballisoftendescribedasthenationalsportoftheUnitedStatesofAmerica,itprobablydevelopedfromaneighteent
ThenumberofresidentswhosenativelanguageisnotEnglishhasrisen34%inthelasttenyearstoapproximately53million,ac
Alaskaisdisappearingslowlybutsurely.Sincethe1950s,itisestimatedthatasmuchas15percentofAlaska’sareahasdisap
Alaskaisdisappearingslowlybutsurely.Sincethe1950s,itisestimatedthatasmuchas15percentofAlaska’sareahasdisap
Whatnumbershouldreplacethequestionmark?
Readthefollowingsentence:FINISHEDFILESARETHERESULTOFYEARSOFSCIENTIFICSTUDYCOMBINEDWITHTHEEXPERIENCEOFYEARS.N
随机试题
表示集中仪表盘面安装的温度记录控制仪。()
欧洲文艺复兴时期,人文主义教育的摇篮是()
与苯巴比妥联用使苯比妥离子化程度增强,减少肾小管的重吸收,降低血药浓度,致疗效降低的中成药不包括
初产妇,30岁。妊娠38周,自然分娩一健康男婴,胎盘正常娩出。产后1小时发现产妇面色苍白,出冷汗,阴道流血量较多,主诉头晕、心慌和口渴。血压90/50mmHg,脉搏120次/分,既往血小板减少症,无高血压及低血压,无贫血史。该种疾病80%以上发生于
投标文件出现下列()情况时,评标委员会不能轻易按废标处理。
中国首次引进DRB的是()项目,随后一批世行贷款项目也开始采用DRB方式。
某企业期末银行存款日记账余额为80000元,银行送来的对账单余额为82425元,经对未达账项调节后的余额为93500元,则该企业在银行的实有存款是()元。
判断一个行业的成长能力,可以考察的方面有()。Ⅰ.需求弹性Ⅱ.生产技术Ⅲ.市场容量与潜力Ⅳ.产业组织变化活动
行政主体做出的行政行为,不论合法还是违法,都推定为合法有效。这说明行政行为具有()。
在Access中,空数据库是指
最新回复
(
0
)