_____________is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying n

admin2018-11-21  19

问题 _____________is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluatin  risk  process effectiveness throughout the project.

选项 A、Identify risks
B、Control risks
C、Plan risk responses
D、Plan risk management

答案B

解析 请参考指定教材的P572。控制风险是在整个项目中实施风险应对计划、跟踪和识别风险、监督残余风险、识别新风险以及评估风险过程有效性的过程。
转载请注明原文地址:https://kaotiyun.com/show/PGXZ777K
0

相关试题推荐
最新回复(0)