( )includes the processes required to ensure that the project includes all the work required,and only the work required.t

admin2019-08-25  41

问题 (        )includes the processes required to ensure that the project includes all the work required,and only the work required.to compete the proj ect successfully.Managing the proj ect scope is primarily concerned with defining and controlling what is not included in the project.

选项 A、Create SCope
B、Project stakeholder management
C、Project scope management
D、Project cost management

答案C

解析 翻译:项目范围管理包含所有必须的工作,并且只包含必须的工作才能成功的完成一个项目。管理项目的范围主要涉及识别与控制不包括在项目中的内容。
    A.创造范围    B.项目干系人管理  C.项目范围管理    D.项目成本管理
转载请注明原文地址:https://kaotiyun.com/show/REUZ777K
0

相关试题推荐
随机试题
最新回复(0)