首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
34
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
What is the main reason for the delay of the construction on Hillcrest Apartments?
选项
A、The bad weather
B、Ineffective supervision
C、Deficient crew size
D、Complex geographical conditions
答案
A
解析
转载请注明原文地址:https://kaotiyun.com/show/RKid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
Mysisteristhreeyears_______thanme.
Wouldyoupleasebuysomemilk,David?There_______inthefridge.
CometoHappyCamp(野营)WhereisHappyCamp?HappyCampisinabeautifulpartofHillLand.Itisjust1,000metersfrom
Manyyearsago,KarlBenzdevelopedacar,butbeforehecouldshowittothepublic,someonehadtodriveit.BertaBenzbeliev
Atlast,we______thesmalltownbeforedark.
Whowillmakeatelephonecall?
A、Iusuallyreadordosomesports.B、Ilikeplayingbasketball.C、Ilikecollectingstamp.B
Farmersdonotlikecrows(乌鸦)becausethesebirdseatnewly-plantedseeds(种子).Theyareafraidthattheywillnothaveanythin
Theteacherwillnotletanyoneleavetheclassroomuntilthebell______.
Weareanetworkofautorepairexpertsworkingtohelpyou(144)chargeofyourautorepaircosts.Withdecadesofexperience,
随机试题
女,38岁,已婚,右乳外上象限可触及一直径3cm包块,同侧腋窝触到肿大淋巴结,其他器官系统未见异常。在询问病史时,对诊断帮助最小的是
对比剂应具备的条件,错误的是
某回迁小区二期项目,总建筑面积22.8×104m2,工程总投资15亿元人民币,框剪结构。建筑层数为地下1层、地上17层。该项目建设单位J公司于2008年5月16日取得《建设用地规划许可证》;于2018年1月29日取得《回迁小区二期项目备案的证明》。截止到事
下列不属于水利水电工程施工进度计划的控制措施的是()。
砌体结构施工时,对砌筑砂浆的技术要求包括()。
注册建造师继续教育证书是其延续注册、变更注册的重要依据之一,注册一个专业的建造师有效期内应参加不少于()学时的继续教育。
如果某房地产的售价为2000万元,其中建筑物1200万元,土地价格800万元,该房地产每年客观收益为180万元,若建筑物资本化率为10%,则土地资本化率最可能为()。
甲公司记账本位币为人民币,20×8年12月31日,甲公司对一项固定资产进行减值测试。该项固定资产原价为800万元人民币,已提折旧150万元人民币,因专门用于国际业务,其未来净现金流量以美元计价,尚可使用3年,各年的现金流量(均发生在年末)分别为30万美元、
专利,有三种含义:(1)专利是指法律赋予专利权人对其获得专利的发明创造在一定范围内依法享有的专有权利。(2)专利是指依法获得专利法保护的发明创造本身。(3)专利是指记载专利技术的公开的专利文献的总和。具体包括记载发明创造内容的专利文献。下列不属于专利的是(
CollegesandUniversities,institutionsofhighereducationthatofferprogramsbeyondthehighschoollevel.Collegesanduniv
最新回复
(
0
)