首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
22
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
What is the main reason for the delay of the construction on Hillcrest Apartments?
选项
A、The bad weather
B、Ineffective supervision
C、Deficient crew size
D、Complex geographical conditions
答案
A
解析
转载请注明原文地址:https://kaotiyun.com/show/RKid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
Weight(体重)isoneofthetaboosubjects.InAmerica,itisOK,orevengood,tobethinbutitisanembarrassment(尴尬)tobeov
Hesaidthatheremembered_______thedoorwhenhecameout.
Thistaskistoodifficult.Ithinkwe’dbetterturn_______himforhelp.
Whowillmakeatelephonecall?
ThenightbeforeIwastohavesurgery(手术),Jeremy,mynine-year-oldson,becameworried."Iamworried【C1】______you,Mom.I’m
A、Iusuallyreadordosomesports.B、Ilikeplayingbasketball.C、Ilikecollectingstamp.B
Mondayisthebeginningoftheworkweek;it’s【C1】_______daymostpeoplelike【C2】_______.It’snot【C3】_______thattheday
InJanuary,1992,Wangrentedahouseforthreeyearsatamonthlyrentof$1,000.WangbecameunemployedinAugust,1992andwa
AccordingtothePhillipsCurve,theeconomycannotbeatfullemploymentandstablepricesatthesametime.
Therefore,itistimeourgovernment______propermeasurestosolvehousingproblems.
随机试题
求曲线y=x2与直线y=0,x=1所围成的平面图形绕x轴旋转一周所得旋转体的体积.
A.活疫苗B.死疫苗C.类毒素D.外毒素E.病原体的部分成分百日咳疫苗是
细菌性痢疾:血吸虫病:
关于糖尿病神经病变以下说法正确的是
有关大隐静脉的描述,下列哪项是恰当的
对于城镇街坊内部隐蔽的界址点及村庄内部界址点,其点位允许误差为()cm。
【背景资料】 某水库枢纽工程总库容1500万m3,工程内容包括大坝、溢洪道、放水洞等,大坝为黏土心墙土石坝,最大坝高为35m,坝顶构造如图1-1所示。 施工过程中发生如下事件。 事件1:为加强工程质量管理、落实质量责任,依据《关于贯彻质量发展纲要
因审计范围受到限制,不能获取充分、适当的审计证据,虽影响重大,但不至于出具否定意见的审计报告时,可以出具无法表示意见的审计报告。( )
下列选项中,有关PowerPoint。演示文稿的表述,正确的一项是()。
Babies’ResponseForsometimeinthepastithasbeenwidelyacceptedthatbabies,andothercreatureslearntodothingsb
最新回复
(
0
)