首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
Wolfe Constructions 121 Fifteenth Street Melbourne 200430 88880000 http: // www. Wolfeco
admin
2011-06-01
25
问题
Wolfe Constructions
121 Fifteenth Street Melbourne 200430
88880000 http: // www. Wolfecon. com
Date: October 3, 2009
TO: Thomas S. Wolfe, President
From: Jack Evans, Project Manager
Subject: Progress on Hillcrest Apartments for September
Construction on the Hillcrest Apartment complex began on August 17 and fell behind schedule almost immediately because of the heavy rains that month.
Current Status
We have not been able to make up the time that we lost in August because of the continuing rain in September. Close supervision and some overtime have prevented us from falling farther behind. We are currently 18 days behind schedule, assuming crew size remains the same and overtime is limited to emergencies only. The foundation for the entire complex is complete. Framing on the 14# townhouse and the gym is complete, and the framers will begin work on the two-bedroom units on Monday, October 6. The electrical and plumbing subcontractors will also begin work on Monday.
Expected Progress
If the weather holds through the rest of this month, I expect to be finished with framing, roofing, and siding by mid-November. That will allow us to begin work on the interiors before the winter rains begin. One possible problem is the shortage of electricians. Our subcontractor has not been willing to consider providing an additional 5 workers to help us make up for some of the time we have lost. Delays on the electrical, will, of course, delay the finish work.
Nevertheless, when we move indoors, we should be able to reduce the total crew by more than 50 percent and begin using the framers and roofers on other projects.
What is the main reason for the delay of the construction on Hillcrest Apartments?
选项
A、The bad weather
B、Ineffective supervision
C、Deficient crew size
D、Complex geographical conditions
答案
A
解析
转载请注明原文地址:https://kaotiyun.com/show/RKid777K
本试题收录于:
托业阅读题库托业(TOEIC)分类
0
托业阅读
托业(TOEIC)
相关试题推荐
Weight(体重)isoneofthetaboosubjects.InAmerica,itisOK,orevengood,tobethinbutitisanembarrassment(尴尬)tobeov
—CanIhelpyou?—Well,I’mafraidtheboxis_______heavyforyou,butthankyouallthesame.
Whowillmakeatelephonecall?
MarawasgoingtostaywithherfriendFannyforthreedays.Aweekbeforehertrip,shecalledFannytotellherwhenthetrain
CometoHappyCamp(野营)WhereisHappyCamp?HappyCampisinabeautifulpartofHillLand.Itisjust1,000metersfrom
Anewcitymaybeexciting,butamovetoanewcitycanbedifficult.Hereareafewwaystogettoknowanewcityanditspeo
talkonmodernmusic_______nextMonday.
Theemployerisvicariouslyliableforatortcommittedbytheemployeeactinginacourseofemployment.
Writealetteraccordingtothefollowingrequest.以甲银行名义,用正式信函格式写一封英文信给乙银行,内容如下:我们感谢你们寄来我们的对账单。在它第4页上,在2006年1月20日有一个
October3rd,2009DearSir,InyoureditorialonAugust31st,thereseemstobesomeconfusedthinkinginattemptingtoestabli
随机试题
关于正常人的体温,正确的是()
目前桥梁用预应力钢材为()。
库存管理的首要任务是根据产品计划的要求确定合理库存。评价库存是否合理的指标是()。
通风机排出的气体压力应为()。
根据通常采用的风险等级评估表,如果某个风险事件将对项目造成中度损失,且发生的可能性很大。则该事件的风险等级为()级。
无公害食品标准是无公害农产品认证的技术依据和基础。目前,我国无公害食品系列标准的主要内容包括()。
将一处大景点分为前后衔接的若十部分来讲解的方法称为_______。
试论述我国四大名绣的名称及其特点。
经济全球化的根本动力是()。
______(要是)thenewsistrue?
最新回复
(
0
)