(70) involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to

admin2019-06-06  22

问题 (70) involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure pertormance.hese other projects can be within the performing organization or outside of it,and can be within the same or in another application area.

选项 A、Metrics
B、Measurement
C、Benchmarking
D、Baseline

答案C