Precedence Diagramming Method(PDM)is a method used in activity sequencing.There are four types of dependencies or precedence rel

admin2018-10-14  37

问题 Precedence Diagramming Method(PDM)is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM.The initiation of the successor activity depends upon the completion of the predecessor activity is called (    ).

选项 A、Finish—to—Start
B、Finish—to—Finish
C、Start—to—Start
D、Start—to—Finish

答案A

解析 前导图法是一种活动排序方法。前导图法有四种依赖或前导关系。后继活动的启动依赖于前导活动的完成,这种关系是完成一开始关系(Finish—to—Start)。
转载请注明原文地址:https://kaotiyun.com/show/VSFZ777K
0

相关试题推荐
最新回复(0)