On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating,activity duration estimating,

admin2014-11-05  33

问题  On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating,activity duration estimating,and(55) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

选项 A、time estimating
B、cost estimating
C、project planning
D、schedule development

答案D

解析
转载请注明原文地址:https://kaotiyun.com/show/VwGZ777K
0

相关试题推荐
最新回复(0)