Why does the summit of the Sydney Harbour Bridge increase?

admin2019-03-06  15

问题 Why does the summit of the Sydney Harbour Bridge increase?
  
W Well, good morning again, everyone, and welcome to "Perspectives" , the weekly New South Wales Radio programme on subjects of general interest from our local area. Today I have in the studio Mr. George Symonds. Good morning, George.
M Good morning, Anne.
W So, what are you going to talk to us about today, George?
M Well, for people from New South Wales and particularly Sydney, this will be of great interest—I hope. I’ m going to tell you a little about Sydney Harbour Bridge.
W Wow! That’ll be so interesting,
M I think so. To start with, I’d like to tell you a little about the size of the bridge. The arch span is 503 metres and the weight of the steel arch is 39,000 tons, (11)The summit is 134m above mean sea level, though it can actually increase by as much as 18cm on hot days as the result of steel expanding in heat. The two pairs of pylons at each end are about 89 metres high and are made of concrete and granite. The steel used for the bridge was largely imported. About 79% came from the United Kingdom but the rest was Australian-made. The granite was quarried in Moroya down the coast, and the concrete is also Australian.
W So, most of the steel used to make our great bridge actually came from England?
M Yes, I’m afraid so. (12)However, the workforce were all Australian!
W Thank God for that. When was the bridge actually built?
M (13)The bridge was opened in 1932 but work first began in 1924, with the construction of the bridge approaches and spans, with two separate teams building the arch on each side working towards each other. The arch was successfully joined on August 19, 1930. I’m afraid that working practices weren’ t very fair in those days and the local government demolished 438 homes which were in the way of the approaches, and as many as 800 families living there were displaced without compensation. The standards of industrial safety were inadequate too. (14)16 workers died during its construction, mainly from falling off the bridge.
W I didn’ t realise that.
M It’ s true. The bridge was formally opened on the 19th March, 1932 by the Premier of New South Wales, Mr. Jack Lang. When it was opened, it was the longest single span steel arch bridge in the world and one of the greatest engineering masterpieces of its time. (15)Several songs were also composed in advance for the occasion but these have now been largely lost or forgotten. However, three postage stamps were issued to commemorate the opening of the bridge and these still exist. One of these stamps, with a face value of five shillings, is now worth several hundred dollars.

选项 A、A long poem.
B、A delicate brochure.
C、Several songs.
D、Three sets of stamps.

答案C

解析 为庆祝大桥的落成,人们谱写了几首歌曲,还为此发行了纪念邮票。但是题干要求的是提前做出的庆祝准备。故选C。
转载请注明原文地址:https://kaotiyun.com/show/WVNK777K
0

随机试题
最新回复(0)