In the process of communication requirement analysis,the project manager should consider the number of potential communication c

admin2014-11-05  35

问题  In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project,s communications.According to Metcalfe’s Law,a project with 10 stakeholders has(7)potential communication channels.

选项 A、10
B、45
C、50
D、100

答案B

解析
转载请注明原文地址:https://kaotiyun.com/show/b8GZ777K