________ is the process of formalizing acceptance of the completed project deliverables.The key benefit of this process is tha

admin2023-02-21  92

问题 ________  is the process of formalizing acceptance of the completed project deliverables.The  key benefit of this process is that it brings objectivity to the acceptance process and increases the  probability offinal product,service,or result acceptance by validating each deliverable.

选项 A、Validate scope
B、Define scope
C、Control scope
D、Collect requirement

答案A

解析 确认范围是正式验收已完成的项目可交付成果的过程。本过程的主要作用,是验收过程具有客观性;同时通过确认每个可交付成果,来提高最终产品、服务或成果获得验收的可能性。A项是确认范围、B项是定义范围、C项是控制范围、D项是收集需求。