The(65) provides the project manager with the authority to apply organizationalresources to project activities.

admin2019-06-06  47

问题  The(65) provides the project manager with the authority to apply organizationalresources to project activities.

选项 A、project management plan
B、contract
C、project human resource plan
D、project charter

答案D