All of followings should be done by the project manager during project control except( ).

admin2013-08-12  26

问题 All of followings should be done by the project manager during project control except(         ).

选项 A、Determine the a change has occurred
B、Ensure that a change is agreed
C、Make sure all changes are approved by management
D、Manage changes as they occur

答案B

解析 下面哪一项不是项目经理在项目控制期间要做的?
    A.Determine the a change has occurred(确定已经发生了变更)
    B.Ensure that a change is agreed(确认某一项变更被批准)
    C.  Make sure all changes are approved by management(确认所有的变更被配置管理系统批准)
    D.Manage changes as they occur(在变更发生时管理这些变更)
转载请注明原文地址:https://kaotiyun.com/show/mdHZ777K
0

最新回复(0)