首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
DEVELOPMENTS IN THE CONSTRUCTION OF TALL BUILDINGS 1 Until the nineteenth century, most tall buildings were constructed of loa
DEVELOPMENTS IN THE CONSTRUCTION OF TALL BUILDINGS 1 Until the nineteenth century, most tall buildings were constructed of loa
admin
2012-01-14
46
问题
DEVELOPMENTS IN THE CONSTRUCTION OF TALL BUILDINGS
1 Until the nineteenth century, most tall buildings were constructed of load-bearing masonry walls. Masonry walls had to be thick, particularly at the base, to support a building’s great weight. Stoneworkers built these walls by placing stone upon stone or brick upon brick, adding strength and stability by placing layers of mortar or cement between the stones. Floors and roofs had to be supported by wooden beams, but the major vertical
force
of buildings was supported by thick masonry walls. This imposed serious limitations on the number and size of windows.
2 In the 1850s, an alternative was emerging that would eliminate the need for exterior weight-bearing walls: a three-dimensional grid of metal beams and columns. The introduction of metal construction made it possible to build larger interior spaces with fewer columns than before. The new construction was capable of supporting all the loads to which a building might be subjected, including the vertical forces caused by the weight of the floors and the horizontal forces caused by the wind or earthquakes.
3 The first buildings to depart from the load-bearing wall tradition were iron-framed. Wrought iron, shaped by hammering the heated metal or roiling it under extreme pressure, contains almost no carbon, and when used as floor beams, it can support a great deal of weight. An interior wrought iron skeleton supported all of the hnilding’s weight. Exterior walls of reinforced concrete acted mainly as weatherproofing.
As masonry yielded to concrete, walls that once bore weight evolved into thin curtain walls that would allow more windows.
These modifications produced sturdier, lighter, and taller buildings that quickly became known as skyscrapers. Skyscrapers satisfied the growing need for office space, warehouses, and department stores. Buildings of eight or more stories quickly transformed the city skyline and dominated the central business districts of American cities such as New York, Chicago, and St. Louis.
4 Skyscrapers differed from previous tall structures with their use of technical innovations such as cast iron and the elevator. The development of cast iron technology, in which molten iron is poured into a mold, made modern plumbing possible. Cast iron pipes, fittings, and valves could deliver pressurized water to the many floors of tall buildings and drain wastewater out. The invention of the mechanical elevator made it possible to construct even taller buildings. Before the elevator, office buildings were rarely more than four or five stories high. In 1857, the first passenger elevator equipped with safety brakes prevented the elevator from falling to the basement when a cable broke. The elevator made the upper floors as
rentable
as the first floor, liberating architecture from dependence on stairways and human muscle.
5 Not only did these innovations have important uses in the engineering of tall buildings, but
they
also erased the traditional architectural distinctions separating the bottom, middle, and top of a building. Architects designed towers that reached to the heavens in a continuous vertical grid. Iron construction established the principle of repetitive rhythms as a natural expression of construction, as well as the idea that buildings could be made of new materials on a vast scale.
6 Construction techniques were
refined
and extended over the next several decades to produce what architectural historians have called "true skyscrapers," buildings over twenty stories high. The invention of steel was particularly significanti as steel T-beams and I-beams replaced iron in these new structures. Steel weighs less than half as much as masonry and exceeds both masonry and iron in tension and compression strength as well as resistance to fatigue. Steel rivets replaced iron bolts and were in turn replaced by electric arc welding in the 1920s. The skyscraper’s steel skeleton could meet all of the structural requirements while occupying very little interior space. Exterior curtain walls could be quite thin, since their only function now was to let in light and keep the weather out.
The word rentable in paragraph 4 is closest in meaning to
选项
A、strong
B、beautiful
C、large
D、desirable
答案
D
解析
Rentable means desirable in this context. Clues: The elevator made the upper floors as rentable as the first floor The elevator meant that people no longer had to climb numerous stairways to the upper floors. Thus, people desired (wanted) to rent the upper floors as much as the first floor. (1.4)
转载请注明原文地址:https://kaotiyun.com/show/qwyO777K
0
托福(TOEFL)
相关试题推荐
Completethesummaryusingthelistofwords,A-H,below.Writethecorrectletters,A-H,inboxes11-13onyouranswersheet.C
Questions5-7Completetheflowchartbelow.ChooseNOMORETHANTWOWORDSfromthepassageforeachanswer.
Completethesummary.ChooseNOMORETHANTWOWORDSfromthepassageforeachanswer.Instrumentssimilartotheguitarhavebee
ChooseTHREElettersA-G.Writeyouranswersinboxes37-39onyouranswersheet.WhichTHREEofthefollowingarefeatu
Completeeachsentencewiththecorrectending,A-E,below.Writethecorrectletter,A-E,inboxesonyouranswersheet.A.
TheInnovationofGroceryStoresA.Attheverybeginningofthe20thcentury,theAmericangrocerystoresofferedcomprehen
AccordingtoMrSingh,onwhichthingdomanypeoplemakesuperficialobservations?MrSinghbelievesthatthebestwaytobes
【21】Whatdoesthetutorgivethestudentalistof?
Gestures—especially______ones.Flashcardscanbedifferentcoloursaccordingtothe______.
WhereisMrGarcialiving?WhycanMrGarciaexpectasmallreductioninrent?
随机试题
溃疡性结肠炎病变多位于
A.甲状腺切除术后呛咳B.甲状腺切除术后音调降低C.甲状腺切除术后呼吸困难D.甲状腺切除术后高热、脉细速、呕吐E.甲状腺切除术后手足抽搐由喉上神经内侧支损伤产生()
以下哪型药疹如系初次用药,其致敏期可在20日以上:
监造的设备从制造厂运往安装现场前,项目监理机构应检查(),并审查设备运输方案。
某工程拟加固改造为商业仓库或生产车间后出租,由业主方负责改建支出和运营维护,或不改造直接出租,此A、B、C三个方案的基础数据见表2—1。折现率为10%,复利系数见表2—2,不考虑残值和改建所需工期。若A、B方案不变,不考虑环境成本、社会收益。C方案改
存货不包括企业的特种储备以及按国家指令专项储备的资产。()
阅读下列材料并回答问题。材料:某初中历史教师王某为新课准备教学设计。她的教学设计流程大体如下。首先,教师通过一个有关商鞅以辕门移木行赏,借此树立在民众中的威信的历史小故事来引出本课所要讲述的内容,即春秋战国时期的社会变革。接着,教师向学生交代几个与本
幼儿园、家庭、()是幼儿发展的三大环境和可利用资源。
下列句子中,标点符号使用正确的是()。
Thetimelimitforthetaskwasonlyoneweek,butsomehowImanagedtogetit______.
最新回复
(
0
)