During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This

admin2010-01-28  11

问题 During the risk analysis process, it is determined that one identified risk event cannot be avoided, mitigated, or insured. This risk event is a critical item that could cause the project to fail if it occurs. The best option for the project manager is to: (73).

选项 A、Continue to search for an insurance company that would assume the risk
B、Place special emphasis on the risk event to intensely manage that item and all interfacing items
C、Play down the risk and the team will find a means of overcoming any failure
D、Ignore the risk assessment because any assigned value is a point estimate which is never precisely the expected state of nature

答案A

解析
转载请注明原文地址:https://kaotiyun.com/show/riHZ777K
0

相关试题推荐
最新回复(0)