( ) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated

admin2019-08-25  33

问题 (        ) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure.

选项 A、Direct costs
B、Operation costs
C、Indirect costs
D、Implement costs

答案C

解析 参考译文  (         )是指不能直接追溯到特定项目的成本,因此可通过一些经过批准和有章可循的会计程序,将其累计并平均分配在多个项目上。
   )A.直接成本    B.运营成本    C.间接成本    D.实施成本