(75) is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period

admin2010-01-28  25

问题 (75) is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

选项 A、Planned value
B、Actual cost
C、Earned value
D、Cost variance

答案C