首页
外语
计算机
考研
公务员
职业资格
财经
工程
司法
医学
专升本
自考
实用职业技能
登录
外语
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer. PROJECT MANAGENT Last week’s definition of pro
Complete the summary below. Use NO MORE THAN THREE WORDS for each answer. PROJECT MANAGENT Last week’s definition of pro
admin
2011-02-08
63
问题
Complete the summary below.
Use NO MORE THAN THREE WORDS for each answer.
PROJECT MANAGENT
Last week’s definition of project management:
Project Management has
a clear【31】
goals, budget and【32】
A project can be divided into【33】
The subject of today’s lecture【34】
LECTURER:
I’d like to begin today with a quick review of last week’s lecture. We saw the definition of project management as something which has a clear beginning and a clear completion date with goals, a budget and a schedule. We saw its presence in the private and public sectors in many different industries. You’ll also remember that we outlined the life cycle as it were, of a project and looked at the first of a four-stage cycle-establishing the limits of the project.
Today, we’re going to talk broadly about the second stage of project management-developing a plan for the project. Next week we’ll focus on the implementation of the project and then, the final stage-its evaluation.
Let’s get started on today’s topic, though-planning the project. The success of a project will depend on the skills and care which you put in at this initial planning stage. Planning is not only necessary in terms of budget or cost, it’s also crucial that you consider the time-frame of a project and the standards which you’ll be expected to provide. These three elements are, of course, integrated. Project-planning is best conducted as a team - you might have to take responsibility for handing over the final plan but without a team behind you, you’ll find it almost impossible to plan effectively.
We’ll discuss budgetary planning firstly because that is, of course, what you are most likely to be evaluated on by your own manager. Before drawing up a budget, you’ll need to understand the time-frame involved to carry out the work and the standard of delivery at which the labour and materials are to be supplied. Now, this is arguably the most difficult to plan for. You’ll never plan completely accurately for a project in terms of money but you will become better at planning realistically. And it is this part of the planning process that you will do last.
The best way to plan the cost of a project is to consider all the factors involved and how those factors relate to time and standard of delivery. Write these down on a spreadsheet format and begin the task of costing and estimating. The company that you’re employed by will always have their own systems in place for doing this. They will also indicate the kind of profit they are looking for-usually in percentage terms.
The second stage of planning is the allocation of time to a project and for this, you’ll have to canvass others for help. Only by asking the advice and opinions of those with expertise in the field, will you be able to establish the size of each unit of work to be completed and the order in which those units of work should be carried out. Remember that some units of work may be done simultaneously but many cannot. In your tutorials this week, you’ll be introduced to the Gant Chart-that’s G-A-N-T. This method of planning project activities has been very successful in the field of project management. The complete set of tasks involved in a project are identified and then planned in relation to each other. You’ll soon discover that organizing and prioritizing activities is quite an art-form.
The third part of your planning as I said, will affect your money and time considerations and that is the standard of delivery that the project demands. These standards will be outlined in the tender documents if they’ve been your guide or the masterplan from which you’re working. Always make sure that you’ve got ALL of the project-related documents that are available. For every unit of work that is to be completed, you’ll have to write specifications-they are detailed descriptions outlining specific standards of quality in materials and labour. If these specifications are not carefully written and then complied with, the project is unlikely to be successful. These specifications will be referred to many times once the project is underway.
You will also have to deal with a Quality Assurance Manager at this stage who will advise you on the standards which need to be met. Quality management has become a valued component in successful project management companies.
I’ve provided you with an outline of the planning process for project management but you’ll be looking at these three elements in more depth in your tutorials this week.
选项
答案
(the/your/this week’s) tutorials
解析
转载请注明原文地址:https://kaotiyun.com/show/zDAO777K
本试题收录于:
雅思听力题库雅思(IELTS)分类
0
雅思听力
雅思(IELTS)
相关试题推荐
Representingaroundworldonaflatsurfaceisimpossiblewithoutsome______:theMercatorprojectionmayshowsGreenlandasov
Abird’splumage,whilecontributingtostructuralintegrityandparticipatinginaeriallocomotion,completelyobscuresabird’
Aslateas1891aspeakerassuredhisaudiencethatsinceprofitablefarmingwastheresultofnaturalabilityratherthan(i)__
Inearly-twentieth-centuryEngland,itwasfashionabletoclaimthatonlyacompletelynewstyleofwritingcouldaddressaworl
ReadthetextbelowandanswerQuestions7-14.INTERCITYSleeperbetweenLondonandScotlandMostticketsmayb
Whereisthestudentfrom?Whatistheproblemmanystudentswithlibrary?
thelibrarytheChurchillBuilding
Themainaimofthefestivalspokespersonatthegatheringisto
Whycan’tPeterrelaxoverthethree-weekvacation?______
TheLibrary
随机试题
人力资源区别于其他资源的最根本的特质是()
下列哪项不属于红细胞过度破坏引起的贫血
下列选项中,对变电所所用电接线要求、备用方式和配置原则的叙述,正确的是什么?
安装调试过程设备监理工程师质量管理的主要任务是( )。
下列关于幼儿园课程评价的说法,错误的是()
对于认知风格属于场依存型的学生,一般情况下,适合的教学方法是()
2011—2015五年期间光缆线路总长度共增加了:
请运用中国法制史的理论知识对下列材料进行分析,并回答问题《唐律疏议.名例律》:“诸犯私罪者,以官当徒者,五品以上,一官当徒二年;九品以上,一官当徒一年。若犯公罪者,各加一年当。以官当流者,三流同比徒四年。”“诸以官当徒者,罪轻不尽其官,留官收赎;官少不
求下列极限:
在窗体上添加一个名称为Command1的命令按钮,然后编写如下事件代码:PrivateSubCommand1_Click()A=75Ifa<60Thenx=1Ifa<70Thenx=2Ifa<80The
最新回复
(
0
)